The management team at the timeshare resort set a tough target.
January 2016 restore all the balconies on both 7 story towers in 6 weeks.
January 2017 remove existing and apply urethane waterproofing system on all balconies on both 7 story towers in 6 weeks.
January 2018 paint the exterior of both towers, apply waterproof coatings to all walkways in 12 weeks.
Did it!
Thanks to a great team effort and the buildings look great.